Pole barn finish budget

Outside barn materials and labor 800
Electrical 600
Concrete 5500
Office  2000
Heater 5000
Insulation 1100 Julie says  3000 now

Total 1700



john 360t
electric supply 161
elelectrical inspection 75
lowes 39
adam 165
paul 75
draingage:456
adam 70
andy 207
John 200
lowes gift cards ordered 2700
 paid andy $100 for pol barn
$50 lumber
concrete 4045
labor for concrete 2200 
parts 320
andy 169
Heater 2500
355 lift and trailer rental 
200 Andy
total: 13892

 Paid Jason 362
Paid Andy 100
Purchased 370 gift cards
Purchased 1900 gift cards
 223 Adam
125 lowes paint chalk
45 one night guy
Dave 50
Dave 125
Dave 125
Other employee 125
Josh 75
Lowes 100
Lift 325